/ SCHEDULE
Project Timeline
The Otahuhu BESS Project is moving from feasibility to commercial operations. Resource Consent is near issuance. Focus now is the path to Financial Close on 1 April 2027, followed by a two-year construction programme and Commercial Operations (COD) on 1 April 2029.
FINANCIAL CLOSE TARGET
Pre-Financial Close — 22-week programme to 1 April 2027
A four-phase programme delivering the six critical-path workstreams lenders and equity partners require before construction capital is drawn:
LIFE SPAN
Start to Finish
TIMELINE